A — Basic information of the case

  • Project Name: Emergency Plan for Construction Site Heat Dissipation

  • Customer Name: China Petroleum Pipeline Bureau Fourth Company

  • Project coordinates:Futian City, Fujian Province

  • Project start time:2016


B — Project Background and Requirements

The Fourth Company of China Petroleum Pipeline Bureau carried out infrastructure construction tasks in Futian in 2016. Due to the need for a large amount of equipment in the project, but the lack of a large cooling equipment system, the progress of the project was slow. Longhe provided an emergency plan after on-site inspection.


C — Solutions and Effects

In response to the customer's need to build a cooling system in the shortest   time and reduce the impact of engineering equipment failures on project progress, Longhe conducted on-site inspections and provided multiple sets of cooling systems consisting of industrial cooling towers and water circulation systems at the project site based on site planning, engineering equipment cooling needs, and total flow rate.


石油01.jpg


D — Customer Acceptance

Machine usage and evaluation:


Installation and use:



Longhe engineers provide on-site guidance and pass the quality inspection



Personnel training:


Teach and train two engineers for the customers



Use Evaluation

Cooling temperature test:

√ Passed

flow rate test:

√ Passed

Pressure test:

√ Passed

noise test:

√ Easy

Overall energy consumption test:

√ Passed


There are dozens of comprehensive evaluation indicators in total, only 5 of which are listed above



②   After sales and other cooperation:


Longhe has provided cooling systems

for multiple engineering projects of

China Petroleum Pipeline Bureau's four

companies since 2016.



E — Project Summary

We have always been committed to providing customers with personalized construction site cooling emergency plans, tailored to local conditions. In the field of personalized equipment customization, we have also been deeply rooted for many years. In terms of equipment quality and after-sales service, we have received praise from many customers and are the best choice for purchasing cooling systems!